Project Update

Skywater at Movala Construction Update

October 14, 2022

Construction at Movala is progressing well and on schedule, here are some exciting new developments:

  • The south tower crane started operating in early September.
  • The second out of eight raft pours was completed in late August, where over 1500 cubic meters of concrete was poured. The third raft pour has just started.
  • 80 out of over 700 piles remain to be completed.
  • Forming and reinforcing vertical elements (walls & columns) has begun in the southwest corner.

Join us on-site at Movala by watching the video below!