Construction at Movala is progressing well and on schedule, here are some exciting new developments:
- The south tower crane started operating in early September.
- The second out of eight raft pours was completed in late August, where over 1500 cubic meters of concrete was poured. The third raft pour has just started.
- 80 out of over 700 piles remain to be completed.
- Forming and reinforcing vertical elements (walls & columns) has begun in the southwest corner.
Join us on-site at Movala by watching the video below!